Recently in move out/move in Category

Moving In

| No Comments

The move into Folwell began this week. Most of the furniture is in place, and the good people of NTS are making the final connections for phones and computers. The space is really enlivened by the bright furnishings--upholstery in crayon bright greens and blues and oranges. The demountable walls are really nice, and the offices have sliding doors reminiscent of being in a Japanese restaurant. Students will love their new spaces.

Final days of the move

| No Comments

As of today, everyone is moved out of Folwell! Abatement has begun on the fourth floor. Here are a few more pics from the last days of the move out.

IMG_7241sm.jpg

Here's what's left of the Spanish & Portuguese office.

IMG_7245sm.jpg

As the building is emptied, extra steps are taken to protect the historic woodwork and flooring. This is the entrance to the GSD library.

IMG_7246sm.jpg

This room was the GSD library. It looks kind of different when it's empty!

IMG_7239sm.jpg

Here's one of the hard-working movers on the ground floor.

Moving Day(s)

| No Comments

The move has begun! Large furniture is being moved off the 4th floor. Some windows along the southeast side are being removed so furniture can be moved out via forklift. Instead of students, the hallways are now full of boxes.

GSDlibrary.jpg

There are still lots of great finds outside the GSD library. Treasure troves of old maps, posters and books can be found in the hallways throughout the building.

SpanPort.jpg

The Spanish and Portuguese department is in the thick of packing. They move out next week.

ScissorLift.jpg

Workers from McGough are readying these windows on the SE side of the building. Lots of Folwell furnishings will be moved out through these windows, placed in a big bin, and lowered by forklift.

ramp.jpg

This is the 3rd floor classroom where the furnishings will be loaded onto the forklift. They will add a ramp to this platform to speed up the emptying of the building.

The move has begun

| No Comments

Some offices in Folwell have already begun moving out of the building. The move will begin in earnest after World Languages Day is over, on Wednesday, May 19. Stop by to watch the clever forklift-rolloff container-ramp apparatus that will help move out furniture via a third-floor window.

If you are wondering where all of the Folwell offices will be located for the remodeling year, download relocation details (PDF).

About this Archive

This page is an archive of recent entries in the move out/move in category.

language learning is the previous category.

Find recent content on the main index or look in the archives to find all content.